The four statements.

Where the sign-offs hinge.

Two critical handoff points:

  1. Consent issue. No PS1 → no consent. Councils will not progress the application without one for any element falling outside Acceptable Solutions (which is almost everything custom-engineered).
  2. Code Compliance Certificate (CCC). No PS3 + PS4 → no CCC. And no CCC means the building legally cannot be occupied or insured.

When statements get withheld.

The most common reasons we see PS4s withheld:

"The PS4 isn't a formality at the end. It's a record that the building was actually built the way the consent said it would be — and councils know it."

How to make this painless.

The bottom line

Producer Statements are the spine of NZ's risk-shifting building consent system. Knowing where they fit changes the way you brief, build, and close a project — and it removes most of the friction with council at consent and CCC.